Tenant Improvement Guide

Budgeting a Tenant Improvement

What drives the cost of a build-out, how a tenant improvement allowance fits in and how to build a budget that holds from estimate to closeout.

Business owners reviewing a commercial office floor plan

What drives the cost

Tenant improvement costs vary widely, so beware of per-square-foot rules of thumb. The biggest drivers are:

  • How much of the existing build-out can be reused
  • Plumbing moves, especially when the slab has to be trenched
  • HVAC condition and capacity
  • Electrical service and equipment loads
  • Change of occupancy requirements
  • Finish level, glass and custom millwork
  • Schedule pressure and after-hours work

Hard costs and soft costs

Hard costs are the construction itself. Soft costs include design fees, engineering, permit and plan review fees, utility and impact fees, testing, furniture, IT, security and moving. Soft costs are easy to forget and can be a meaningful share of the total, so list them from day one.

Using the tenant improvement allowance

Many leases include an allowance the landlord pays toward the build-out. Know how it is paid (in progress payments or at completion), what it can be used for and what documentation is required. Read our guide to tenant improvement allowances.

Contingency and change control

Carry a contingency for unknown conditions, especially in older or second-generation spaces. Decide on finishes early, approve changes in writing with a price and schedule impact, and review the budget at every meeting.

Planning a Nevada build-out?

Share the suite address, approximate square footage and the date you need to open. A Nevada project manager calls back to set up a walk-through.

Common questions

Have a question about your space that is not answered here? Call and speak with a Nevada project manager.

Ranges are wide and depend on the space and use. We give you a written estimate after walking the space rather than relying on averages.

Many owners carry a contingency on top of the construction cost, higher for older spaces with unknown conditions.

We state clearly which fees are included. Some fees, such as impact or utility fees, are often paid by the owner.

Finish the design before pricing, walk the space thoroughly and make decisions early.